Dear Residents: This email was sent by the Association attorney regarding the roofs. “As expected, the insurer retained an engineering firm – Rimkus – to inspect the roofs and damaged units. We are in the process of coordinating the inspection with those owners whose units have damage. As of now, the inspection will be set
Month: December 2022
Roof Inspections
Stratus Roofing will be out for another inspection on roofs, December 8th between 8:30 am to 12:00 pm. If you address is listed below, please reach out to jknapp@stratusfroofing.com to schedule your availability as they will need to get into your home.
Drainage Repair
Repair work to connect the drainage system from the Townhomes to the master drain is tentatively scheduled on Monday, December 12th. The work will be performed on the drainage located on Derby Park Alley and connect it to the main drain on Vermillion Ave. The work will be done in the area between unit 11939